Party Wall Surveys Explained: When You Need One and How It Works

When the Party Wall etc. Act 1996 applies, the notices and timings involved, what a party wall award and schedule of condition are, and who pays.

By Chris Anslow, RPSA-certified principal surveyor · Updated

You need a party wall surveyor when building work falls under the Party Wall etc. Act 1996 and your neighbour does not agree to it in writing. The Act covers work to a shared wall, a new wall on the boundary, and excavation close to a neighbour's foundations. When it applies, notice must be served, and if the neighbour dissents or does not reply, surveyors agree an award that sets out how the work may be done.

The Act exists to let building work go ahead while protecting the neighbour's property. Handled early, it is a routine part of an extension or loft conversion. Handled late, it can hold a project up for weeks.

When the Party Wall Act applies

The Act covers three kinds of work in England and Wales:

  • Work to an existing party wall or structure. Cutting into a shared wall to insert a steel beam, raising or thickening it, underpinning it, or cutting off projections. This is the usual one for loft conversions and rear extensions on terraced and semi-detached houses.
  • A new wall on the boundary line. Building a wall astride or right up against the boundary.
  • Excavation near a neighbour's building. Digging within 3 metres of a neighbour's building or structure to a lower level than the bottom of its foundations, or within 6 metres where the excavation would cut a 45-degree line down from them.

Work that is not covered, such as most internal alterations, needs no party wall notice, though it may still need planning permission or building regulations approval.

Notices and timings

The owner planning the work (the "building owner") serves notice on the neighbour (the "adjoining owner"):

  • Party structure notice: at least two months before work to an existing party wall or structure.
  • Line of junction notice: at least one month before building a new wall on the boundary.
  • Notice of adjacent excavation: at least one month before excavating near a neighbour's foundations.

The neighbour has 14 days to respond. They can consent, in which case the work goes ahead on the terms of the notice, or dissent. If they do not respond at all within 14 days, the Act treats that as a dispute.

Surveyors, the award and the schedule of condition

When there is a dispute, the owners either appoint one "agreed surveyor" between them, or each appoints their own surveyor. The surveyors then draw up a party wall award: a document that sets out the work that may be done, how and when, and how access and protection will be handled.

Most awards include a schedule of condition: a written and photographic record of the neighbour's property before work starts. If cracks or other damage appear later, they are judged against that record, which protects both sides. Even where a neighbour consents, recording the condition of their property first is sensible, and we can do that on its own.

The owner doing the work usually pays the surveyors' reasonable costs, including a surveyor appointed by the neighbour.

If you are the neighbour

If you have received a notice, you do not have to agree. Consenting is quick and costs nothing; dissenting means surveyors are appointed, at the building owner's expense in most cases. Either way, ask for a schedule of condition of your property before work starts. If cracks appear during or after the work, our guide to cracks in walls explains which ones matter, and a property defects survey, from £450, can investigate a specific problem.

Party wall surveys from Anslow

We provide party wall surveys and advice under the Party Wall etc. Act 1996, including schedules of condition, across Greater Manchester and Cheshire, including Chester. Every party wall matter depends on the work proposed and who is serving notice, so contact us with the details and we will confirm how we can help. Chris Anslow is a member of the Residential Property Surveyors Association with around twenty years' experience.